Granville Street Roadwork will tackle sewers and sidewalks over the next six months

Published: September 30, 2025

Granville Street roadwork to tackle sewer and sidewalk rehabilitation

Sewer upgrades on Granville Street

The work will begin this weekend – starting at 8 PM on Friday, September 26th – with sewer upgrade work on Granville Street between West 59th and 64th Avenues.

The City’s contractor will begin installing a sewer manhole at the intersection of W 64th Avenue and Granville Street starting Friday, September 26the at 8:00 PM. Work will continue around the clock through 5:00 AM on Monday, September 29th.

Following this, weekday construction (Monday to Friday) will take place only at night, between 8:00 PM and 5:00 AM. The contractor will distribute letters in the coming days to provide the community with more details about the upcoming construction.

Most of this work is overnight, but note some weekend work in the Construction Timeline Grid below.

Granville Street Roadwork will fix sewers and sidewalks over the next six months

Sidewalk Rehabilitation

The long-awaited sidewalk rehabilitation project will begin in mid-October. This work will involve fixing and replacing the damaged and heaving sidewalks between W 63rd and W 64th Avenues with new concrete sidewalks.

Access to all residences and business to be maintained at all times

Construction Timeline (Tentative Schedule subject to change)

Time period Location and work Work hours Traffic measures/impacts
Sept 26, 2025 – Jan 2026 Sewer upgrades on Granville St between W 59th Ave and W 64th Ave) Overnight work (8 pm and 5 am) on weekdays

Work at intersections will take place 24/7 on weekends

Granville St
Nighttime: 4 lanes closed; 2 lanes open

Daytime: 3 lanes closed; 3 lanes open

Mid Oct. – Nov. 2025 Sidewalk rehabilitation (W 64th – W 63rd Ave) – Access to all residences and business to be maintained at all times Daytime work (7 am – 5 pm)

Daytime: 1 lane closed; 5 lanes open

Jan. – Mar. 2026 Sewer upgrades on W 59th Ave (Granville – Cartier St) and W 62nd Ave (Granville – French St)

Daytime work (7 am – 5pm) W 59 Ave: Full road closure 24/7 between Granville & Cartier

W 62 Ave: Full road closure 24/7 between Granville & French

 